The Second Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (TIIGP 2) is designed to help transform secondary GMS central and southern corridor towns into economically inclusive, competitive international tourism destinations by improving road and water transport infrastructure, urban environmental services, and capacity to sustainably manage tourism growth. It will boost trade in services and deepen regional cooperation and integration among the GMS and Association of Southeast Asian Nations (ASEAN). About 88,000 residents are expected to directly benefit from climate-resilient infrastructure development and increased access to economic opportunities.
The project will increase Cambodia and Lao PDR’s share of ASEAN’s international visitor arrivals from 8.0% to 8.3% and project areas will receive 700,000 more international tourists. This will increase aggregate annual visitor expenditure from $0.55 billion to $0.91 billion.
Project Areas in Lao PDR
- Nationwide
- Luang Prabang Province
- Vientiane Province
- Champasak Province
Project Outcome
Tourism competitiveness of secondary towns in the Lao PDR increased
Project Outputs
The Project includes the following seven infrastructure subprojects, which packaged into five works packages, as follows:
1) Works Package: TIIGP2-LAO-W01: Nakasang and Don Det-Don Khone Access Improvements
Subproject C1: Nakasang Access Road and Port Rehabilitation
Subproject C2: Don Det-Don Khone Access Improvements
2) Works Package: TIIGP2-LAO-W02: Nam Ngum Reservoir Access Improvements
Subproject V1: Nam Ngum Reservoir Access Improvements
3) Works Package TIIGP2-LAO-W03: Kaeng Yui Waterfall Access Improvements and Western Loop Rural Access Road and Bridge Improvements
Subproject V2: Kaeng Yui Waterfall Access Improvements
Subproject V3: Western Loop Rural Access Road and Bridge Improvements
4) Works Package TIIGP2-LAO-W03a: Vang Vieng Urban Renewal
Subproject V4: Vang Vieng Urban Renewal
5) Works Package: TIIGP2-LAO-W04: Vang Vieng Landfill Improvements
Subproject V5: Vang Vieng Solid Waste Management Improvements
2) Support the implementation of selected ASEAN Tourism Standards and the ASEAN Sustainable Tourism Awards
2) build capacity for infrastructure operation and maintenance (O&M) through the preparation of O&M plans and training to implement the plans.
Project Implementation Period
2019 – 2024
Project Budget
Source | Amount (Million USD) | Share of Total |
Asian Development Bank | 47 | 96,30 % |
Government of Lao PDR | 1,8 | 3,70 % |
Total Budget | 48,8 | 100 % |
Executing Agencies (EA)
Ministry of Information, Culture and Tourism
This post is also available in: Lao